Facts & Figures

 ClientMunicipality of Strömstad
 LocationStrömstad, Sweden
 Operation Start2018
 WastewaterMunicipal
 Project TypeGreenfield
 Process ConfigurationPre-treatment + Primary settler + Nereda
 Nereda Design Capacity:
  • Dry Weather Flow4 MLD
  • Peak Flow360 m3/h
  • PE21,000 PE (PE = 60 gBOD/d)

About the Strömstad Nereda WWTP

Designing a wastewater treatment plant for the municipality of Strömstad is challenging for two reasons. First: Strömstad is located in a very touristic area of Sweden, which means that the variation in loading is large throughout the year. Second: the low temperatures during the winter may not affect the treatment results.